Connect the wires according to the operation requirements of the electric fusion welding machine, and set the correct welding parameters of the electric fusion welding machine, which can be input manually or actively.
After checking, start the electric fusion welding machine to enter the welding process. When the welding time is reached, the machine will actively enter the cooling state.
When the pipe fittings are completely cooled, remove the electric fusion welding machine.
Cut the pipe with a plastic pipe cutter or a fine tooth saw with a cutting guide device, and make its end face perpendicular to the pipe axis. Use a knife to cut the burr at the internal edge, scrape the welding area at the pipe or socket end, and tidy up the welding area.
Special clamps shall be used as far as possible to fix the components to be connected. The roundness of the pipe shall not exceed 1.5% of the pipe outer diameter, or it shall be calibrated on the corresponding clamps.
The pipes and pipe fittings shall have suitable gaps, which are generally suitable for penetration with slight force. Too large or too small gaps will affect the quality of the interface.
Check the penetration depth, slide the bell fitting into the C] end of the spigot and position it correctly.